This project involved the installation of all process specific chemical and bulk gas systems throughout the facility. The chemical systems consisted of 10,000-20,000 gallon bulk tanks and bulk delivery units that supply a chemical distribution unit to feed the fabrication facility. Materials used include PVDF, Teflon, stainless steel tubing, carbon steel pipe, and double containment piping. JBH installed all the bulk delivery systems and piping into the building from bunkers located away from the primary building. The bulk gases were then fed to the main valve box, a distribution valve box and then to a valve manifold box. JBH also installed all of the inert gases for the area. Lines were run from the inert gas room cabinet throughout the building.